On some Implementations of Solving the Resource Constrained Project Scheduling Problems
Yugoslav journal of operations research, Tome 29 (2019) no. 1, p. 31
Cet article a éte moissonné depuis la source eLibrary of Mathematical Institute of the Serbian Academy of Sciences and Arts
We consider a resource-constrained project scheduling problem with respect to the makespan minimization criterion. The problem accounts for technological
constraints of activities precedence together with resource constraints. Activities preemptions are not allowed. The problem with renewable resources is NP-hard in the
strong sense. We propose an exact branch and bound algorithm for solving the problem
with renewable resources. It uses our new branching scheme based on the representation
of a schedule in form of the activity list. We use two approaches of constructing the
lower bound. We present results of numerical experiments, illustrating the quality of the
proposed lower bounds. The test instances are taken from the library of test instances
PSPLIB.
Classification :
90B35, 90C27, 90C59
Keywords: Project Management, Resource Constrained Project Scheduling Problem, Renewable Resources, Cumulative Resources, Branch and Bound Algorithms, PCPLIB
Keywords: Project Management, Resource Constrained Project Scheduling Problem, Renewable Resources, Cumulative Resources, Branch and Bound Algorithms, PCPLIB
@article{YJOR_2019_29_1_a1,
author = {E.Kh. Gimadi and E.N. Goncharov and D.V. Mishin},
title = {On some {Implementations} of {Solving} the {Resource} {Constrained} {Project} {Scheduling} {Problems}},
journal = {Yugoslav journal of operations research},
pages = {31 },
year = {2019},
volume = {29},
number = {1},
language = {en},
url = {http://geodesic.mathdoc.fr/item/YJOR_2019_29_1_a1/}
}
TY - JOUR AU - E.Kh. Gimadi AU - E.N. Goncharov AU - D.V. Mishin TI - On some Implementations of Solving the Resource Constrained Project Scheduling Problems JO - Yugoslav journal of operations research PY - 2019 SP - 31 VL - 29 IS - 1 UR - http://geodesic.mathdoc.fr/item/YJOR_2019_29_1_a1/ LA - en ID - YJOR_2019_29_1_a1 ER -
%0 Journal Article %A E.Kh. Gimadi %A E.N. Goncharov %A D.V. Mishin %T On some Implementations of Solving the Resource Constrained Project Scheduling Problems %J Yugoslav journal of operations research %D 2019 %P 31 %V 29 %N 1 %U http://geodesic.mathdoc.fr/item/YJOR_2019_29_1_a1/ %G en %F YJOR_2019_29_1_a1
E.Kh. Gimadi; E.N. Goncharov; D.V. Mishin. On some Implementations of Solving the Resource Constrained Project Scheduling Problems. Yugoslav journal of operations research, Tome 29 (2019) no. 1, p. 31 . http://geodesic.mathdoc.fr/item/YJOR_2019_29_1_a1/